Destia is the contractor of phase 1 of the E18 Kausela-Kirismäki project in 2019-2021. The project is implemented as a design-build-develop contract. The goal of the project is to improve the safety and flow of traffic and create new opportunities for developing the are and planning land use.

The project includes removing level crossings between Kausela and Kirismäki and constructing gour lanes in the Pukkila-Kirismäki section. The Kirismäki multi-level interchange is improved and the Pukkila multi-level interchange is constructed. In addition, the project includes constructing the Sippaa overpass, implementing the parallel lanes of the ring road and National Road 10 improvement works between ring road and Tammitie.

The project in numbers:

  • Ring road serves 13,500 vehicles per day
  • The improvement works will raise the speed limit to 100 km/h in the four-lane section

Customer: Finnish Transport Infrastructure Agency

Contract time: 2019-2021